Completed projects at operating plants

Mill and flotation machine installation, processing plant audits, hydraulics service and joint commissioning with Metso:Outotec.

  • 6 projects
  • since 2017

Equipment installation, Bakyrchik gold recovery plant

Polymetal JSC · 2017 · Installation supervision
01
768tonnes · MPSI 6.7×5.65 and MShTs 5.0×8.0 mills195 days
558tonnes · Skim Air-1200 flotation machines (2 cells), TC-160 (7), TC-70 (7), TC-50 (5), TC-30 (9)57 days
170tonnes · HRT13м thickener, CAVEX 500cvx10 hydrocyclones, 34 Weir Minerals screens79 days
99.6tonnes · crushing section: CJ-615 crusher, SG1841 screen, YPT HD-P 1800×12000 feeder23 days
Equipment installation, Bakyrchik gold recovery plant

Equipment installation and dismantling, Amursky Hydrometallurgical Combine

Amursky Hydrometallurgical Combine LLC · 2018 · Installation supervision
02

Filter press installation MFP 2016 07 50/50 M60 complete with a filter cloth washing system.

Motor control cabinet installation (MCC) for the filter.

Filter cloth wash pump KSB Multitec MTCA 50/10 B-3.1.

Acid wash pump Warman 4/3C-AH, A51/A52, CV, N=15 kW, h=27.5 m.

Pump Warman 100VE-GPS, C26, N=11 kW, h=7.5 m, Q=87 m³/h.

Equipment installation and dismantling, Amursky Hydrometallurgical Combine

Audit and throughput increase strategy for a gold recovery plant

Audit · Development
03

Technical and process audits Gold recovery plants No. 1–4 for KBE.

Strategic directions for increasing throughput Gold recovery plant No. 4 with flowsheet calculations up to 8 Mt/year for KBE, Polyus Gold JSC.

Process maps, maintenance, repair and lubrication charts for equipment; preparation for the rollout of ERP systems (maintenance module).

Audit and throughput increase strategy for a gold recovery plant

Hydraulic systems service, Altyntau Kokshetau gold recovery plant

Maintenance
04

Hydraulic systems service ball mills, roller presses and cone crushers.

Hydraulic systems service, Altyntau Kokshetau gold recovery plant

Technical and process audit of processing plants No. 1, 2

Audit
05

Comprehensive technical and process audit of processing plants №1 and №2 AMK LLP, Cetco.

Technical and process audit of processing plants No. 1, 2

Joint projects: installation supervision and commissioning

8 sites
06

Installation supervision, commissioning and start-up of equipment together with Outotec at eight sites:

  • Albazino
  • Mayskoye
  • Kubaka
  • Omsukchan
  • Zyryanovsk processing plant
  • Ridder processing plant
  • Altyntau Kokshetau
  • Gaisky GOK
Joint projects: installation supervision and commissioning

Trusted by

Polymetal Polyus Kazzinc NLMK Cetco Metso:Outotec
Contact us

Still have questions?

Send us an enquiry and our manager will contact you shortly.

By clicking Send, you consent to the processing of personal data